By 24 November 2022, Enemalta and Nexans had completed major repair works on the Malta–Italy interconnector at Qalet Marku, cutting out over 1.5 km of anchor‑damaged cable, removing the cast iron shells, installing a new spare cable section stored at Delimara Power Station, and jointing it aboard the cable vessel Nexans CVL Aurora, in a campaign costing around €25 million to enable the interconnector to be re‑energised.