Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By the end of December 2014, all equipment installation and cable jointing works for the Malta–Sicily interconnector in both Malta and Sicily had been completed, following earlier laying of the approximately 98km subsea cable between December 2013 and March 2014, leaving the 120km, 220kV HVAC interconnector ready for system testing and subsequent commissioning.