Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Offshore cable installation for the Malta–Sicily interconnector’s roughly 98 km subsea circuit was completed by March 2014, with the C/S Nexans Skagerrak finishing laying the 220 kV subsea cable between Marina di Ragusa in Sicily and Qalet Marku in Malta as part of Enemalta’s 200 MW interconnection to the Italian grid.