Onshore construction works at the Magħtab terminal station for the IC2 project, including extensive cable laying beneath switchgear, installation of new cable boxes and sealing ends, and installation of 132kV cable between the GIS and transformer, were reported as ongoing and having reached key milestones at the Magħtab site in March 2026. This confirms that onshore substation civil/electrical works for IC2 were underway by March 2026.