Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Onshore construction for the Malta–Sicily Cable Link 2 (IC2) began in the fourth quarter of 2024, with works starting at the Maghtab terminal station in Malta and at the Ragusa substation area in Sicily following the issue of the Italian construction permit in Q3 2024.