In July 2025, InterConnect Malta reported that additional sections of the onshore cables for the second Malta–Sicily interconnector were being manufactured in Turkey under tender CT3003/2024, while the first Factory Acceptance Test was completed on 50 km of fibre-optic cable, which was then shipped to the United States for assembly into the subsea cable under tender CT3008/2024.