Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
SELT SpA was awarded a €34.2 million contract for the manufacture, trenching, installation and restoration of IC2’s onshore high‑voltage cables, comprising approximately 21 km from Marina di Ragusa to the Ragusa 220 kV substation in Sicily and 1.8 km between l‑Għallis and the Magħtab terminal in Malta.