Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
By November 2014, Red Eléctrica had started excavation and conservation works on an archaeological site located within the premises of the Torrent substation in Ibiza as part of the environmental requirements for the Majorca–Ibiza interconnection (Rómulo 2). The company committed over 700,000 euros to this archaeological project within a broader 2.2 million euro programme of preventive and corrective environmental measures designed to minimise the new link’s impacts on natural habitats and cultural heritage.