Red Eléctrica's 2015 Corporate Responsibility Report states that in 2015 "the laying and installation of the first cable of the Majorca-Ibiza link was carried out" and estimates that the second cable would be brought into service in the first months of 2016. This confirms that submarine cable installation activities for the Rómulo 2 Mallorca–Ibiza interconnection had begun by 2015, using dedicated cable-laying vessels as previously announced.