Red Eléctrica's 2017 "Copa del Rey" monograph states that the submarine electricity link between Mallorca and Ibiza (Rómulo 2) was "finalizado en el 2016" (completed in 2016), describing it as a 126 km, 132 kV AC double-circuit submarine interconnection linking the Balearic subsystems. This indicates that installation and protection of the Mallorca–Ibiza submarine cables were completed in 2016, later than the original 2015 plan.