Lynn is an offshore wind farm in the southern North Sea (The Wash) off the Lincolnshire coast near Skegness, with a nameplate of 97.2 MW delivered by 27 Siemens 3.6 MW machines and developed as the paired site to Inner Dowsing. The two adjacent Round 1 sites were combined for planning and construction and together (Lynn + Inner Dowsing) provide 194 MW from 54 turbines. Lynn was taken through consent and construction in the mid-2000s: site-specific geotechnical and wave modelling informed foundation design, a 2006 test pile programme validated drivability in chalk, foundations and array cabling were installed in 2007, and turbine installation and commissioning completed around 2009. Installation works used specialist assets (for example the M.V. Resolution installation vessel) and Nexans supplied the submarine export and array cables. Commercially the project was developed and initially operated by Centrica Renewable Energy; Centrica sold a 50% stake in the combined Lynn & Inner Dowsing development to TCW in October 2009 (public reporting at the time). Lynn’s role is primarily a Round‑1, nearshore UK project that helped establish early operational experience for larger North Sea developments; its paired layout with Inner Dowsing and the early divestment of equity are the notable commercial features. Sources report commissioning and first exports in 2009 and document the test-pile, foundation and cable contractors involved.
Monopile⌀ 2 m · 65 m long · embed 25.5 m · 50 mm wall
Project used driven steel monopiles. A site-specific test monopile was driven at Lynn in April 2006 (single steel monopile test). Geology required some local drilling to reach design depth.
Power-Technology reports a combined construction cost of £300 million for Lynn and Inner Dowsing. Brunel (contractor recruitment page) cites a higher figure (£529m for Phase 1), so there is a...
Source states the submarine cables were supplied 'along with a fibre‑optic element' but gives no fibre count or further detail; likely included for operational/telecom/SCADA use, but no number or leasing...
Cables included a fibre-optic element (unspecified number of fibres/cores) incorporated into the 36 kV 3-core XLPE submarine cable system — likely for turbine/control communications and telemetry; no fibre pair/count or...