Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In October 2014 the export cable for the Eneco Luchterduinen wind farm made landfall on the Dutch shore near Noordwijk, marking the start of offshore export cable installation between the beach and the offshore high-voltage substation. The cable, to carry power from 43 turbines (129 MW total), was installed from shore by the cable-laying vessel Ndurance and buried using the Trenchformer tool over the following approximately two weeks.