Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By October 2014 VBMS had completed installation of the export cable for the Eneco Luchterduinen offshore wind farm. Using the cable-laying vessel Ndurance and the multi-purpose trencher Trenchformer, the company laid and buried the approximately 25-kilometre, 150 kV export cable connecting the offshore high-voltage station to the Dutch shore.