Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Nexans Norway SA was awarded a EUR 100 million contract by the London Array developers to design, manufacture, and supply four 150 kV XLPE high‑voltage subsea export cables, each 53–54 km long with integrated fibre optics, to connect the London Array offshore substations to the Cleve Hill grid connection point in Kent.