On 15 February 2013 SKM issued its final report "Review of the London Array Export Cable Costs and the Cleve Hill Incident" for Ofgem, providing an independent assessment of the London Array export cable installation costs and the additional costs associated with repair works at the Cleve Hill 400 kV onshore substation, to support Ofgem’s process of setting the final transfer value for the London Array OFTO transmission assets.