The Energinet-sourced notice "Elkabler over Lillebælt forsvinder" (Maritime Danmark) and the Ingeniøren article "Verdens tykkeste trefasede 400 kV-kabel lægges ud i Lillebælt" state that Energinet is laying two 400 kV submarine cables in Lillebælt and Fænø Sund, with the first cable being installed from 17–22 June 2013. This shows that submarine cable installation started on 17 June 2013.