In May 2024, Next Geosolutions commenced a detailed cable route survey in UK waters for the LionLink multi‑purpose interconnector between the UK and the Netherlands. The campaign, starting on or around 15 May, covers marine geophysical, nearshore and intertidal surveys, marine geotechnical investigations, and ROV utility‑crossing surveys along corridors from the Walberswick and Southwold landfalls that join and run northeast towards the Dutch Exclusive Economic Zone, with several dedicated survey vessels deployed for approximately 156 days.