As part of the consent process for the Lincs project, a FEPA marine licence was issued allowing installation of two export cables from the offshore substation to a landfall east of the mouth of the River Nene, with conditions restricting cable installation activities in the intertidal zone to the period from 15 May to 31 August to protect over‑wintering birds.