Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Erection of the 48 Siemens 2.3 MW turbines at the Lillgrund offshore wind farm started in 2007, with the machines installed sequentially onto the previously placed gravity-based foundations as part of the main construction phase.