Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Installation of Lillgrund’s subsea cable system started in mid‑December 2006, when offshore laying of the export and inter‑array cables commenced following prior trench excavation. This campaign initiated the placement of the 33 kV internal array network and the high‑voltage export connection between the offshore substation and the onshore Bunkeflo substation.