Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Cable installation at Lillgrund was completed by July 2007, concluding the laying of approximately 22 km of 33 kV inter‑array cables and the 130 kV export cable between the offshore substation and the onshore grid connection at Bunkeflo. Despite weather‑related delays and vessel issues, the full offshore cable system was in place ahead of final commissioning later in 2007.