Latvia and Estonia Hybrid Offshore interconnector [currently known as 'Elwind']
2022
Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
In 2022, AST and Elering completed a detailed onshore right‑of‑way study for possible onshore connection options and prepared a technical catalogue study to assess available technologies, solutions, and indicative costs for the offshore transmission infrastructure needed for the ELWIND hybrid project and the associated fourth Estonia–Latvia interconnection.