Significant progress or notable issue
On 19 March 2024, Nexans announced it had secured the first call-off under TenneT’s 2GW framework agreement, an Engineering, Procurement, Construction and Installation (EPCI) contract for the high-voltage direct current (HVDC) cable systems for the BalWin3 and LanWin4 offshore grid connection systems transmitting power from the North Sea to Wilhelmshaven in Germany.