Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 15 January 2025, Nexans and TenneT signed the project‑specific agreement for the LanWin2 offshore grid connection in Germany, confirming Nexans as the cable EPCI contractor under the earlier framework. The EUR 1 billion contract covers the engineering, procurement, construction, and installation of about 250 km of 525 kV HVDC XLPE onshore and offshore export cable systems to transmit 2 GW of offshore wind power from the German North Sea to the mainland grid connection point in the Heide area of Schleswig‑Holstein, with commissioning expected in 2030.