Neutral
Informational - no clear directional impact
Low Impact
Minor progress or informational
On 30 May 2024, LS Cable & System commenced production of the first 525 kV DC cables at its Donghae facility in South Korea under TenneT’s framework agreement with the Jan De Nul Group, LS Cable & System and Denys. This marks the start of cable manufacturing for the BalWin4 and LanWin1 2 GW offshore grid connection projects, with the initial high-voltage direct current cables specifically intended for these connections.