As part of KONČAR’s contract for HOPS, Asso.subsea was engaged by KONČAR to perform transportation and installation of approximately 30 km of 110 kV submarine cables in Croatia, including the Krk–Cres interconnector between Mali Bok and Merag and the Cres–Lošinj link at Osor bay. The scope comprised offshore cable laying in waters up to 70 m deep, three 630 mm² replacement cable systems along the old routes, and technically challenging onshore pull‑in operations using HDD pipes and custom‑designed rollers on steep coastal slopes.[51]