Minor progress or informational
On 15 February 2017, an application titled "Zahtjev za ocjenom o potrebi procjene utjecaja" was submitted for the 110 kV submarine cable Krk (Mali Bok) – Cres (Merag), together with an environmental protection study describing the replacement of the existing cable with a new XLPE-insulated 110 kV cable along the existing route. The filing, recorded under class number 351-03/16-04/1522 and reference 517-06-2-1-2-17-4, sought a determination under the Croatian EIA Regulation that the project falls under item 2.6 "Transmission of electricity by lines of 110 kV and higher within the transmission network" and is thus subject to the environmental impact assessment screening procedure.