Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In 2016, engineering firm Dalekovod Projekt d.o.o. completed the conceptual design and routing for the replacement 110 kV submarine cable link between KS Mali Bok on Krk and KS Merag on Cres. The idejni projekt defined an approximately 7.46 km route (about 91 m onshore on Krk, 7,190 m subsea, and 179 m onshore on Cres), largely following the existing cable corridor with a ~20 m offset, and specified that the new XLPE cable with integrated optical fibers would be installed in underground trenches onshore and parallel to the existing seabed alignment offshore.[4][6][19][21]