Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
On 15 December 2016, Energinet.dk and 50Hertz awarded NKT Cables a contract for the Kriegers Flak Combined Grid Solution to manufacture, deliver and lay the submarine cables connecting the Danish Kriegers Flak offshore wind farm with the German offshore wind farm Baltic 2 in the Baltic Sea. The two AC submarine cables supplied under this contract will enable the transfer of around 400 MW of energy between the Danish island of Zealand and the German federal state of Mecklenburg-Western Pomerania.