Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
VBMS (contracted by NKT) commenced installation of approximately 50 km of 150 kV AC submarine cables for the Combined Grid Solution (Kriegers Flak) in Q2 2018. Both offshore cables confirmed in place by July 2018. Cable commissioned 5 June 2019.