Three 220 kV three-core submarine cables (~100 km total) connecting Kriegers Flak A and B to Rødvig, incl. 44 km from each platform to shore and 11 km between platforms.
ABB won an order from Energinet.dk to design, supply and install a 220 kV HVAC submarine cable system for the Kriegers Flak offshore wind farm grid connection to Denmark. The scope comprised three 220 kV three-core submarine cables with a total length of about 100 km, including two export cables from the Kriegers Flak A and B platforms to the Danish landfall at Rødvig and an inter-platform cable between the two offshore platforms.