Following the January 2022 fault, NKT executed a subsea repair campaign on the 285 kV Konti-Skan 2 mass-impregnated HVDC cable, locating the damage about 33 km offshore from the Swedish converter station, cutting out the damaged section using a third-party repair vessel, jointing in a replacement length, and reburying the cable at a safer water depth to reduce future external impact risks.