Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
By mid‑2023, Energinet and 50Hertz completed the two‑stage replacement of KONTEK’s HVDC cable system, including a 150‑km onshore and submarine section under Energinet’s responsibility and a further ~15 km of underground onshore cable in Mecklenburg‑Western Pomerania replaced by 50Hertz, after which the new route was commissioned and the interconnector returned to operation.