ENTSO-E’s Baltic Sea Regional Investment Plan identifies Kontek‑2 (project DKE‑DE), a 600 MW HVDC subsea interconnector between Denmark‑East and Germany, as a TYNDP 2016 future project candidate with an expected commissioning year of 2030, intended to further integrate electricity markets and renewable generation in both countries.
Licence: Inclusion as TYNDP 2016 project candidate
Kontek‑2 (listed as project DKE‑DE), a 600 MW HVDC subsea interconnector between Denmark‑East and Germany promoted by 50Hertz and Energinet.dk, was included as a future project candidate in ENTSO‑E’s TYNDP 2016 process via the Baltic Sea Regional Investment Plan. The consultation document, published on 24 June 2015, describes it as a 600 MW link called Kontek‑2 with an expected commissioning year of 2030 and the purpose of further integrating markets and renewables in both countries.
| Denmark | GE | |
|---|---|---|
| Landfall | — | — |
| Grid Connection | Bjæverskov Static Inverter Plant (Bjæverskov substation), Zealand, Denmark | Bentwisch Static Inverter Plant (Bentwisch substation), near Rostock, Germany |
Denmark
GE