Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Global Marine Systems commenced installation of the northern 33 kV subsea export cable and five inter-array cables for the Kincardine Floating Offshore Wind Farm in July 2020, using the cable installation vessel Normand Clipper. The campaign ran from July 2020 to September 2021 and included post-lay testing, onshore export cable jointing, and termination at the floating asset. The work was delayed from the original Q2 2020 plan, likely due to COVID-19.