100% ROC+ 1 PPA
Kincardine Offshore Windfarm Limited (KOWL) has set out an indicative decommissioning programme for the Kincardine floating offshore wind farm in its 2018 Decommissioning Programme, planning to begin decommissioning activities in 2043 at the end of the project’s 25‑year design life, with options including potential repowering or leaving export cables in situ subject to conditions at that time.
GEOxyz completed a full subsea inspection campaign at the operational Kincardine Floating Offshore Wind Farm, using ROVs to inspect 15 mooring lines, five inter-array cables and two export cables in support of KOWL’s planned maintenance requirements.
Kincardine Offshore Windfarm Limited (KOWL) issued a Notice to Mariners advising that a short ROV-based survey programme of the Kincardine field—covering both export cables, the mooring lines of each of the five units, and all inter-array cables—would start no earlier than 15 August 2025 and last approximately 3–4 weeks to support operational inspection of the floating wind farm assets.
Authority: Marine Scotland · Licence: Project Environmental Monitoring Plan (PEMP) for Kincardine Offshore Windfarm
On 3 April 2025, a Project Environmental Monitoring Plan (PEMP) for the Kincardine Offshore Windfarm was submitted to Marine Scotland as a post‑consent document, defining the project’s environmental monitoring commitments during operation.
In spring 2024, Acteon began an 18‑month operations and maintenance programme for the Kincardine Offshore Wind Farm, involving design, supply and installation of integrated structural health and motion monitoring systems on the floating turbines and the development of a structural response digital twin to support anomaly detection, optimise inspections and enable potential asset life extension.
The full 50 MW Kincardine Floating Offshore Wind Farm, comprising six turbines including five 9.5 MW units on WindFloat semi‑submersible foundations located about 15 km off Aberdeen, entered operational service at full capacity, with the turbines generating clean energy from October 2021 and power being taken under a long‑term power purchase agreement with Statkraft.
By September 2021, with all six turbines in place at the Kincardine floating offshore wind farm, the installation of the associated floating WindFloat semi‑submersible foundations in 60–80 m water depths south‑east of Aberdeen was effectively complete, providing platforms for one 2 MW and five V164‑9.5 MW turbines.
Global Offshore, part of the Global Marine Group, announced it had been awarded a contract by Spanish developer Grupo Cobra to install and bury one export cable and five inter-array cables at the Kincardine Floating Offshore Wind Farm, using the cable installation vessel Normand Clipper for a total of 30.3 km of cable.
Global Offshore carried out offshore boulder clearance and cable route preparation using a pre-lay plough at the Kincardine Floating Offshore Wind Farm site southeast of Aberdeen in spring 2020, ahead of export and inter-array cable installation. Note: date is from pre-event contract announcement; confirmed indirectly by cable installation starting July 2020 (SPIE Wind).
Global Marine Systems commenced installation of the northern 33 kV subsea export cable and five inter-array cables for the Kincardine Floating Offshore Wind Farm in July 2020, using the cable installation vessel Normand Clipper. The campaign ran from July 2020 to September 2021 and included post-lay testing, onshore export cable jointing, and termination at the floating asset. The work was delayed from the original Q2 2020 plan, likely due to COVID-19.