Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In August 2012, Hellenic Cables completed the installation of an approximately 8.6 km, 12/20 kV 3x95 mm² Cu/XLPE submarine cable interconnection between Thasos and Keramoti for the Public Power Corporation of Greece (DEI). The turnkey scope covered loading the cable directly onto a cable-laying vessel at the Fulgor port, laying and protecting the cables at the shore ends and on the seabed, providing land/submarine transition joints, spare and repair joints, carrying out all jointing and termination works, and performing testing and commissioning for the two new island interconnections, including Thasos–Keramoti.