Positive
Project advancing - milestone achieved
High Impact
Major milestone or critical setback
Turbine installation at the 49.5 MW Kentish Flats Extension was completed on 10 August 2015, after which the turbines began generating power via the extension export cable system to the Red House Farm substation. All 15 turbines were generating power to the National Grid from 12 September 2015.