Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Export and inter-array cables for the Kentish Flats Extension were loaded onto the cable-lay vessels BoDo Installer and Nostag 10 at Nordenham, Germany, on 1 May 2015, with the BoDo Installer completing loading by 5 May 2015. The vessels then transited to the site off the south-east coast of England where cable installation commenced later in May 2015.