Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
Energinet’s 7 July 2025 press release "Arbejdet med at lægge søkabel ud mellem Hellerup og Amager går i gang i juli" announces that the company is about to start installing the KBH05 subsea cable between Amagerværket, Nordhavn and Hellerup, and that this work "går i gang i juli" (starts in July). The release is dated 7 July 2025 and provides detailed operational information and safety instructions for other sea users, indicating that the start of submarine cable installation is imminent and scheduled for the same month. There is no later public information indicating that this marine installation campaign was postponed. Given this, I treat the start of cable installation for KBH05’s subsea cables as occurring in July 2025 and record it with month-level precision.