Positive
Project advancing - milestone achieved
Low Impact
Minor progress or informational
Vattenfall’s official Kattegatt Syd project page states that archaeological investigations are being carried out in the wind farm area and the offshore export cable corridor during August–November 2025, including ROV-based seabed surveys offshore and visual diving/probing nearshore. This matches the planned campaign of archaeological investigations for the wind farm site and export cable route, so the start of the “other survey” campaign can be confirmed as August 2025.