Johan Sverdrup phase 2 (Electrification)
Approximately September 2019
Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
After the summer of 2019, Aibel commenced the main construction phase for the Johan Sverdrup Power from Shore II onshore converter plant at Haugsneset east of Kårstø under an EPC contract for Equinor, starting civil and installation works that would double converter capacity and enable shore power for Johan Sverdrup Phase 2 and the wider Utsira High area.