Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In 2019, ahead of commissioning the Italy–Montenegro HVDC interconnector between Cepagatti (Villanova) in Italy and Lastva in Montenegro, Terna’s Dispatching unit carried out system preparation and testing activities. Working with the Montenegrin TSO, it drew up operational rules, conducted connection tests on the new 500 kV DC link, and prepared for auctions to allocate the 600 MW cross‑border transmission capacity.