Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In September 2023, Terna completed laying the 132 kV submarine power cable between the island of Elba and Piombino (LI), a new interconnection approximately 37 km long, including 34 km undersea and 3 km of fully underground cable. The installation was carried out to high environmental sustainability standards, including the repositioning of around 53,000 cuttings of Posidonia oceanica seagrass in the Gulf of Follonica to protect the local marine habitat.