On the first weekend of April 2017, after repair jointing of the damaged Isles of Scilly 33 kV subsea cable was completed, Wootton & Wootton returned to perform final VLF pressure testing with the HVA200 on the fully reconnected circuit from St Mary’s back to the Cornish mainland, testing both while the new joint was on the repair vessel and again after it was lowered to its final seabed position prior to re‑energisation on 4 April 2017.