Neutral
Informational - no clear directional impact
Medium Impact
Significant progress or notable issue
Following the March 2017 anchor strike on the 33 kV, 55 km subsea cable between Land’s End and St Mary’s Power Station, Western Power Distribution initiated a full repair campaign, including fault location, deployment of the cable repair vessel CS Sovereign with an ROV to cut and lift the damaged section, subsea jointing works, and associated high-voltage testing, culminating in completion of repairs that enabled reconnection of the Isles of Scilly to mainland power in early April 2017.