Following catastrophic anchor damage to the 55 km, 33 kV subsea cable supplying the Isles of Scilly, Wootton & Wootton used their HVA200 VLF test set from St Mary’s Power Station in early March 2017 to carry out pre‑repair pressure testing of the island‑to‑fault section, manually operating at 0.01 Hz and 32.47 kV for 30 minutes to confirm the integrity of the cable up to the break.