Cyclades Interconnection Phase D : Santorini - Folegandros - Milos - Serifos
June 2025
Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
According to IPTO’s interim condensed financial report for the first half of 2025, the protection works for the submarine high-voltage cables on the Milos–Folegandros and Folegandros–Thira interconnections, including burial and related offshore safeguarding activities, were completed in June 2025. This finalized the offshore cable protection phase for the Folegandros–Thira segment of Cyclades Interconnection Phase D.