Cyclades Interconnection Phase D : Santorini - Folegandros - Milos - Serifos
February 2025
Positive
Project advancing - milestone achieved
Medium Impact
Significant progress or notable issue
In February 2025, IPTO reported that the submarine high-voltage cable for the Folegandros–Thira (Santorini) interconnection had been laid as part of Cyclades Interconnection Phase D, completing the offshore cable installation between the two islands. This work was executed alongside the Milos–Folegandros link to integrate the southwestern Cyclades into the High Voltage System.