MT Højgaard A/S installed all monopile foundations and transition pieces at Inner Dowsing (27 monopiles), using the MPI Resolution heavy-lift jack-up vessel as part of the twin-site campaign with Lynn (54 monopiles total). Foundations were installed by end of 2007, with cable and turbine works following through 2008.